Côte d’Ivoire’s Integrated Programme for Development and Adaptation to Climate Change in the Niger Basin (PIDACC/BN) handed a livestock facility to Baya’s herders on 15 October 2026, according to the public news agency’s 17 October report. The reported construction cost is FCFA33 million. This establishes a named programme handover, not payment records or attribution to the US$24.07 million additional package. The immediate decision is to establish inclusive management under the sub-prefect and clarify operating resources, alongside the remaining November–December delivery commitments.
Latest assessment
A livestock facility at Baya has been handed to herders; its operating arrangements remain open. The Ivorian public news agency reports a 15 October handover in Baya, Boundiali department, Bagoué region. It identifies FCFA33 million as the construction cost and records a recommendation for an inclusive management committee under the sub-prefect. Committee formation, operating resources and finance attribution are not established.
Decision now due
Establish Baya’s management and operating resources, and evidence the remaining dated deliveries. The management committee was recommended as soon as possible on 15 October, without a fixed deadline. Gbéléban and Gbémou landing facilities remain due by 30 November; structural works by 31 December 2026. The additional-finance phase closes on 31 December 2027. Verify committee appointment, supervision, user access, upkeep and operating resources. Training and a livestock-water borehole were requested, not delivered. Obtain the contract, payments and funding component for Baya. The source calls it a livestock park; it does not explicitly identify it as the previously announced loading station, so that milestone is not marked fulfilled by inference.
Verified action
Five verified response entries now include the reported Baya handover. Preparation, launch, supervision, the ministry’s initial-programme execution report and Baya’s handover are documented. This is a count of response entries, not five completed infrastructure projects. The handover report does not establish sustained operation, increased incomes or reduced conflict.
Open evidence
Baya’s management, water provision and finance attribution remain open, as does the additional-package cash trail. FCFA33 million is a reported construction cost, not an independently traced payment or additional-finance release. The file needs committee appointment, operating and maintenance arrangements, water provision, procurement and payment records. Additional-package drawdown, counterpart release, regional allocations and attributable outcomes remain open. No evidence in this file is not proof of no action.
Responsibility
The Ministry of Water and Forests and its national coordination unit hold the Ivorian implementation chain. The ministry’s Director-General of Water Resources represented the minister at Baya. An inclusive local management committee was recommended under the sub-prefect; its appointment remains open. Regional committees and technical services support the programme, and the Niger Basin Authority coordinates its regional component.
Decision trace
- T0 · Signal · Verified
The Ivorian component of PIDACC/BN has moved from an existing resilience programme into an additional-financing phase covering climate adaptation, landscape restoration and natural-resource management in eight regions.
- T1 · Trigger · Verified
The agreements were signed on 13 March 2026. The Council of Ministers adopted three ratification decrees on 3 June, before the additional-financing launch on 16 September. The African Development Bank announcement followed on 28 September.
- T2 · Authority · Mapped
The Ministry of Water and Forests and the PIDACC/BN National Coordination Unit lead national implementation. Regional monitoring committees connect prefects, regional councils, decentralised technical services, financial control and programme accounting. The Niger Basin Authority coordinates the regional component.
- T3 · Commitment · Verified
The launched package totals US$24.07 million: an African Development Fund loan of US$6.87 million, a Forest Investment Programme loan of US$12.6 million and grant of US$1.9 million, plus a US$2.7 million Ivorian counterpart contribution.
- T4 · Execution · Verified
Baya’s livestock-facility handover on 15 October is reported by the public news agency. The ministry’s earlier initial-envelope aggregate remains a separate baseline. The new handover does not establish which financing component paid for it, sustained operation or fulfilment of the separately described loading-station milestone.
- T5 · Outcome · Not assessable at this stage
Not yet. Existing programme outputs form a baseline, but the additional-financing phase requires separate evidence of hectares restored, water and livelihood assets delivered, beneficiaries reached and resilience outcomes by the end of 2027.
Programme territory
This is programme and decision-trace evidence, not a hazard classification.
- Bagoué · North-west · Execution reported. Baya, Boundiali department: livestock facility handed over on 15 October; management and operating evidence open. FCFA33 million construction cost reported; payment and funding-component attribution not evidenced in this file. Baya committee appointment, operating resources, water supply, maintenance and attributable finance; wider additional-phase delivery.
- Kabadougou · North-west · Execution reported. Launch or post-launch programme action is documented in this file. No region-specific allocation or release is evidenced in this file. Region-specific work plan, procurement award, contract and completed delivery under the additional financing.
- Folon · North-west · Execution reported. Launch or post-launch programme action is documented in this file. No region-specific allocation or release is evidenced in this file. Region-specific work plan, procurement award, contract and completed delivery under the additional financing.
- Gbêkê · Centre · Execution reported. Launch or post-launch programme action is documented in this file. No region-specific allocation or release is evidenced in this file. Region-specific work plan, procurement award, contract and completed delivery under the additional financing.
- Bélier · Centre · National programme only. The region is within the official programme geography; additional-financing execution is not yet documented here. No region-specific allocation or release is evidenced in this file. Region-specific work plan, procurement award, contract and completed delivery under the additional financing.
- Iffou · Centre · National programme only. The region is within the official programme geography; additional-financing execution is not yet documented here. No region-specific allocation or release is evidenced in this file. Region-specific work plan, procurement award, contract and completed delivery under the additional financing.
- Moronou · Centre · National programme only. The region is within the official programme geography; additional-financing execution is not yet documented here. No region-specific allocation or release is evidenced in this file. Region-specific work plan, procurement award, contract and completed delivery under the additional financing.
- N’Zi · Centre · National programme only. The region is within the official programme geography; additional-financing execution is not yet documented here. No region-specific allocation or release is evidenced in this file. Region-specific work plan, procurement award, contract and completed delivery under the additional financing.
Finance
- Baya livestock facility: FCFA33 million · Reported construction cost; financing attribution open. The handover report gives a construction cost, not a contract, release or payment record. It does not identify the additional package as the funding source. Management training and a livestock-water borehole were requested; no financing or delivery of either is established.
- Initial PIDACC/BN envelope: FCFA 13 billion · More than FCFA 10 billion reported disbursed. The Ministry of Water and Forests reports the aggregate disbursement and physical execution above 80% for the existing programme. The file does not yet contain transaction-level records, a regional allocation schedule or evidence that this aggregate belongs to the additional-financing package.
- African Development Fund loan: US$6.87 million · Ratified and launched. The Council of Ministers records ratification of the loan agreement. The public file does not yet show the drawdown schedule, amount released or expenditure by subproject.
- Forest Investment Programme loan: US$12.6 million · Launched; release evidence open. The AfDB launch statement identifies the loan component. Component-level disbursement, regional allocation and payment records have not yet been entered in this file.
- Forest Investment Programme grant: US$1.9 million · Ratified and launched. The Council of Ministers records ratification of the grant agreement. Ratification is not treated as proof that the full grant has been disbursed or spent.
- Government counterpart contribution: US$2.7 million · Committed; release evidence open. The AfDB launch statement identifies the Ivorian contribution. The appropriation, release and expenditure trail remain to be published or entered in this file.
Principal sources
- Agence Ivoirienne de Presse · Baya handover: Published 17 October; reports the 15 October handover, FCFA33 million construction cost, committee recommendation and requests for training and livestock water. No attribution to the additional financing or outcome evaluation.
- Côte d’Ivoire Council of Ministers: Ratification of the additional-financing loan and grant agreements
- Ministry of Water and Forests: Programme launch, national coordination, regional monitoring and field supervision
- Ministry of Water and Forests · implementation report: Initial-envelope disbursement, physical execution and dated infrastructure delivery commitments